This walk-through follows a used 120 m³/h batching plant being moved from a European site to an infrastructure project site in East Africa. It describes our standard process rather than one specific customer contract. In our experience this sequence takes 14–18 weeks from initial site inspection to full commissioning, depending on vessel schedules and customs speed at the destination.
The plant was a 2018 120 m³/h plant with a documented production history of total production. It had been well maintained by its previous owner — a European civil engineering firm — with complete service records, original manuals in European and English, and a documented parts history. The mixer liners had been replaced 8 months before the move and were in good condition. The electrical system was Siemens S7-1200 PLC with a Siemens HMI. The main structural steel showed minor surface rust but no section loss. We classified the plant as "Good — ready for relocation with standard preparation." The valuation was performed by an independent machinery appraiser, which was essential for the destination-country import customs process.
A team of four dismantling technicians typically spends 8–14 days on site. The dismantling followed our standard procedure: full photographic documentation, colour-coded tagging of every electrical cable (52 cables, 14 terminal blocks), numbered flange tags on all material and pneumatic pipes, and component-to-container mapping before any container was loaded. The plant filled two 40 ft flat-rack containers (mixer unit, silo sections, structural steel) and one 40 ft high-cube container (control panel, screw conveyors, weigh hoppers, spare parts, and tools). All electronic components were packed in VCI film with desiccant. The total packed weight was 42 tonnes. A special challenge was the twin-shaft mixer — at over 12 tonnes, it required a 50-tonne mobile crane for loading and custom steel cradles welded into the flat-rack container to prevent movement during sea transit.
The containers are trucked to the loading port and shipped to the destination port (typical transit 18–25 days depending on routing and transshipment). The shipping route was chosen for direct service — avoiding transshipment in a hub port reduces both risk and timeline. the destination country's import procedures required a Certificate of Used Machinery (issued by a recognised inspection agency), a clean inspection report from the European side, and a full packing list and commercial invoice. Customs duty was calculated at 10% of the CIF value, plus 16% VAT — a predictable cost that was included in the project budget. Our local clearance agent in the destination port pre-filed the customs documentation while the ship was still at sea, so the containers cleared customs within 3 days of arrival.
The containers arrived at the destination port Port on Day 0. Customs clearance took 3 days. Trucking to the project site took 2 days. On-site installation began on Day 6 with a crew of six (two from our team, four locally hired). The foundation was already prepared by the client based on our drawings. Structural assembly took 5 days, mechanical installation 6 days, electrical wiring 4 days, and calibration/commissioning 2 days. The plant produced its first concrete batch on Day 25 after container arrival — 19 days of on-site work. The contractor was producing commercial concrete for their road project by the end of week 3. The total on-site time was within the planned schedule and well within the time frame typical for plants of this size.
How the total cost splits: site inspection and condition survey 3–5%, dismantling and packing 15–20%, consumables (VCI film, desiccant, timber, cradles) 3–5%, ocean freight 12–18%, marine insurance 2–4%, customs duties and clearance 8–15%, inland trucking to site 4–8%, installation and commissioning 25–32%, travel and accommodation 5–8%. Actual figures depend on plant model, distance, port pair and duty rate in your country.
The relocation cost is a fraction of a new equivalent plant, and the exact ratio depends on the model and the duty rate at destination."cta">
Need help with your batching plant? Contact our team for a free consultation.
Talk to our engineers directly on WhatsApp for a fast response.
Chat on WhatsAppParts: Wear Parts & Structural Items · Mixer & Mixing Parts · Conveyor & Transport Parts · Silo & Cement System Parts
Services: Relocation Service · Maintenance & Repair Service