Frequently Asked Questions

What soil bearing capacity is needed?

HZS60: 150 kN/m2, HZS120: 200 kN/m2, HZS180: 250 kN/m2. Site must have natural drainage.

What are the foundation design requirements?

HZS60: 4x4x0.5m, C25, 12mm rebar. HZS90: 5x4x0.6m, C30, 14mm. HZS120: 5x5x0.8m, C30, 16mm. HZS180: 6x5x0.8m, C35, 16mm.

How do you build a foundation step by step?

1) Excavate 500-800mm. 2) Compact granular base. 3) Install rebar with anchor bolts using template. 4) Set formwork level. 5) Pour concrete continuously. 6) Cure 7-14 days.

What are the most common foundation mistakes?

Poor soil investigation, wrong anchor bolt placement (always use template), insufficient curing (wait 14 days), poor drainage, undersized silo foundation.

How much does foundation construction cost?

HZS60: $5,000-$8,500. HZS90: $7,500-$12,000. HZS120: $10,000-$15,000. HZS180: $13,000-$20,000. Expect 20-30% higher in Africa.